<National Grid News>:Transmission of the Anhui electric power to the west project started GIS installation

Number of visits: Date:February 6,2013

 

On Nov 29th, the 1100kv GIS provided by Pinggao Group to the Transmission of the Anhui electric power to the west project got installed. the circuit breaker module and disconnector module was docked successfully that day.

 

Pinggao Group was to provide 14 bays of 1100kv GIS, 4 sets of 1100kv bus bar for Huainan and Huxi substation of the project. the installing personnel arrived the Huainan substation on Oct 25th. Through effective communication and good preparation, the GIS arrived the substation on time and got docked successfully.